Sr. |
Project Description |
Project Name |
Project Deliverables |
End Client |
1 |
Propane Refrigeration Package 321 TR/ Minus 31.9˚C Refrigeration System |
Propane Refrigeration Package |
3D Plant Modeling , Piping GA, Piping Isometrics, BOQ, Support Drawings, Piping Stress Analysis,
Process Calculations sheets, H&M Balance Calculations, Mechanical Design & Detailing, Fabrication
Drawings, etc. |
IOCL, Baroda EIL Voltas India |
2 |
Detailing of Metering Skid & Pressure Regulating Skid for Naphtha Gas |
Dahej Nagothane Ethane Pipeline |
3D Plant Modeling , Piping GA, Piping Isometrics, BOQ, Support Drawings, Piping Stress Analysis,
Process Calculations sheets, H&M Balance Calculations, Mechanical Design & Detailing, Fabrication
Drawings, etc. |
GE Oil & Gas, L&T, Reliance Gas Pipelines Ltd |
3 |
Design of LPG Storage Facility |
LPG Storage Facility Project |
3D Plant Modeling , Piping GA, Piping Isometrics, BOQ, Support Drawings, Piping Stress Analysis,
Process Calculations sheets, H&M Balance Calculations, Mechanical Design & Detailing, Fabrication
Drawings, etc. |
Bharat Tank & Vessels |
4 |
Piping Stress Analysis, Structural Analysis & PDMS Modeling. |
DANGOTE OIL REFINERY COMPANY, LEKKI, NIGERIA |
3D Plant Modeling , Piping GA, Piping Isometrics, BOQ, Support Drawings, Piping Stress Analysis,
Civil & Structural Analysis |
DANIEL MEASUREMENT SOLUTIONS PVT. LTD. |
5 |
EXPANSION PROJECT |
BHUTAN BREWERIES EXPANSION PROJECT |
P&ID diagram for steam line, BOQ for accessories , BOQ for Piping and Fittings, Isometrics for steam
line, Stress Analysis report for steam line, Node isometrics drawing for steam line. |
PRAJ INDUSTRIES LTD. |
6 |
AS BUILT PROJECT |
BHUTAN CENTENNIAL DISTILLERY, BHUTAN |
Piping Stress Analysis of steam lines, Pressure drop calculations, line sizing, bulk MTO, support
drawings, insulation thickness calculations & Isometrics. |
PRAJ INDUSTRIES LTD. |
7 |
Turbine Installation |
Roquette Riddhi Siddhi Pvt. Ltd., BELGAVI (KARNATAKA |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
Roquette Riddhi Siddhi Pvt. Ltd |
8 |
Turbine Installation |
SHIV Edible, Kota |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
SHIV Edible |
9 |
Turbine Installation & As built |
SHIV HEALTH, Kota |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification, Pressure drop calculations, line sizing, bulk MTO, support drawings, insulation
thickness calculations & Isometrics. |
SHIV HEALTH |
10 |
Turbine Installation & As bulit |
Shri Venkateshwara Biorefinery & Biofuels Pvt. Ltd. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification, Pressure drop calculations, line sizing, bulk MTO, support drawings, insulation
thickness calculations & Isometrics. |
Shri Venkateshwara Biorefinery & Biofuels Pvt. Ltd. |
11 |
Stress Analysis of lines connected to Pump, Blowers, Tanks, and UG lines |
GANGA JAL PROJECT UNIT, UPJNL |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
Voltas Limited |
12 |
Stress Analysis of Large Bore Water Lines connected to Pump and UG lines. |
KARNATAKA POWER CORPORATION LTD. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification. |
Voltas Limited |
13 |
Piping Stress Analysis of entire package of Feed Pump, Cartridge Filter Lines |
IOCL-PARADIP-ETP |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification. |
VA TECH WABAG LTD. |
14 |
45 MLD TTRO FOR CMWWSB KOYAMBEDU |
CMWWSB KOYAMBEDU |
Piping Stress Analysis of GRP LINES, Stress Analysis & Report, Stress Isometrics, Support Drawings,
Nozzle load chart, Spring & Bellow specification. |
VA TECH WABAG LTD |
15 |
TTRO and Transmission system for Koyambedu TTRO Project |
|
Piping Stress Analysis of TTRO and Transmission system, Stress Analysis & Report, Stress Isometrics,
Support Drawings, Nozzle load chart, Spring & Bellow specification |
VA TECH WABAG LTD |
16 |
Extension of pipe rack and addition of cold temperature line |
As built Project
|
Equipment Layout & Civil information drawings , Piping Layout & Isometrics
Drawings for statutory approval
Fabrication drawings of piping iso and equipment
|
Deepak Fertilizers,
Aarvi Encon
|
17 |
Piping Stress Analysis of entire Plant. |
HPCL Lube Oil Building Plant |
Stress Analysis & Report, Stress Isometrics, Support Drawings |
Aarvi Encon,
HPCL Lube Oil
|
18 |
Piping Stress Analysis of Steam Lines |
Vardhman Fabrics. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
Steam Fuel, Vardhman Fabrics |
19 |
Stress Analysis of Steam lines connected to Turbine |
Parag Agro Foods Ltd. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
Parag Agro Foods Ltd. |
20 |
Stress Analysis of Turbine Line & Steam Lines |
TURBINE INSTALLATION |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification, Piping isometrics, etc. |
AARTI INDUSTRIES LIMITED |
21 |
Stress Analysis of Turbine Line |
TURBINE INSTALLATION, MALANPUR, M.P. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
GODREJ CONSUMER PRODUCTS LTD. |
22 |
Piping Stress Analysis of Mounted Bulled Outlet Nozzle |
LPG Mounded Bullets at Numahligarh Refinery Ltd. |
Stress Analysis &Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
FABTECH PROJECTS & ENGINEERS LTD |
23 |
Stress Analysis of Turbine Line |
TURBINE INSTALLATION, Vadodara |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
DEEPAK NITRITE LIMITED |
24 |
Stress Analysis of Turbine Line |
SAINATH ORGANIC SUGAR & AGRO PVT. LTD |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
Nilason,
SAINATH ORGANIC SUGAR & AGRO PVT. LTD
|
25 |
Stress Analysis of Turbine Line |
BOILER & TURBINE INSTALLATION |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
EMBIO LIMITED |
26 |
Piping Stress & Civil Structural Analysis |
H-ENERGY, Dabhol & Jaigarh |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart,
Structural Analysis, Beam optimization, Lifting Lug Location & Foundation Loads Calculations |
DANIEL MEASUREMENT SOLUTIONS PVT. LTD., |
27 |
Technip (10 Skids) |
28 |
Air Products |
29 |
Black & Veatch |
30 |
BECHTEL & RELIANCE (7 Skids) |
31 |
BPCL, KOCHI & EIL |
32 |
RCF-GAIL |
33 |
RASISSA OIL TERMINAL & SNC LAVALIN, INDIA |
34 |
GAIL, LTD. |
35 |
Stress Analysis of Turbine Line |
CAMLINE FINE SCIENCE LTD. TARAPUR. |
Stress Analysis Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring & Bellow
specification |
HI – CHEM TECHNOLOGY |
36 |
Piping Stress Analysis of Steam & Condensate Piping, Support Drawing |
KUMAR METAL INDUSTRIES PVT. LTD |
Stress Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring specification |
KUMAR METAL INDUSTRIES PVT. LTD |
37 |
Analysis of riser down comer piping |
M.E ENERGY PRIVATE LIMITED,. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
M.E ENERGY PRIVATE LIMITED, |
38 |
Stress Analysis of Pipes connected to Tanks |
ONGC, Hazira Project |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
ORBITINDIA ENGINEERING CONSULTANCY SERVICES |
39 |
PLAN DIRECTOR OF GAS FLOW OF THE SANTOS BASIN – ROUTE 3 |
PETROBRAS. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
PRAJ INDUSTRIES LTD. |
40 |
60 KLPD AA MSDH PLANT |
REGOLA BIOCHEMICAL PVT LTD |
41 |
400 KLPD FUEL ETHANOL |
DISTILLERIA RIOPAILA S.A.S. |
42 |
480 M3/DAY FUEL ETHANOL (DISTILLATION + 800 M3/DAY MSDH) |
INGENIO Y REFINERÍA SAN MARTÍN DEL TABACAL S.R.L. |
43 |
Gas Treatment Plant Western Lindero 3 |
TECNA. |
44 |
600 KLPD FUEL GRADE ETHANOL |
AUSTCANE ENERGY PVT. LTD. |
45 |
300,000 LPD OF ANHYDROUS ALCOHOL |
INCAUCA SA. |
46 |
Piping Stress Analysis of Steam & Condensate Piping, |
INDIAN SUGAR MANUFACTURING CO. LTD. |
47 |
250,000 LITS/DAY ANHYDROUS ALCOHOL |
INGENIO PROVIDENCIA S.A. |
48 |
150,000 Lit/Day Anhydrous Alcohol |
Manuelita S.A |
49 |
200,000 Lit/Day Anhydrous Alcohol |
ATANOR S.C.A, ARGENTINA. |
50 |
60 K LITRES PER DAY DISTILLERY |
KAKIRA SUGAR LIMITED |
51 |
400 KLPD FUEL ETHANOL |
DIN SUAY NUM CO. LTD. |
52 |
50,000 LITERS PER DAY RECTIFIED SPIRIT |
KOOLL COMPANY INC, PHILIPPINES |
53 |
60 KLPD TS MOLASSES BASED DISTILLERY |
SWARAJ INDIA AGRO LTD. |
54 |
50 KTA OF ETHYL ACETATE PURIFICATION PLANT |
PRAIRIE CATALYTIC, LLC. |
55 |
FALLING FILM EVAPORATOR |
IOCL. |
56 |
EVAPORATION PLANT FOR 280 M3/DAY |
JSW STEEL COATED PRODUCTS LTD |
57 |
600 KLD MULTI EFFECT EVAPORATIO PLANT |
VARDHAMAN FABRICS. |
58 |
600 KLD MULTI EFFECT EVAPORATIO PLANT |
GRASSIM |
59 |
ETHANOL RECOVERY UNIT |
AMYLUM BULGARIA EAD(ADM). |
60 |
Stress Analysis of Jacketed Pipes |
PET FLAKES PROJECT, Barabanki |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
RELIANCE INDIA LIMITED, AARVI ENCON |
61 |
Stress Analysis of Jacketed & Non Jacketed Line |
PET FLAKES PROJECT, Alahabad. |
Stress Analysis & Report, Stress Isometrics, Support Drawings, Nozzle load chart, Spring
specification |
RELIANCE INDIA LIMITED, AARVI ENCON |